Project Portfolio Management (PPM )“Unprocessed Costs”

PPM strictly enforces business rules to ensure costs are within project start and end dates. When a cost is passed to PPM that is outside of the project start and end dates, it results in an “unprocessed cost” error and the transaction cannot post to the contract or grant. Although all applications feeding financial information...